Hyderabad Growth Corridor Limited (A Joint Venture of HUDA and INCAP) has taken up the construction of eight-lane access controlled expressway as Outer Ring Road to Hyderabad City Phase-II A (Bongulur to Tukkuguda) from Km 108 to Km 121 – Contract Package – AP4 is part of Outer Ring Road to Hyderabad City. Maytas Infra is one of the Consortium members for the Concessionaire. The length of this project is 13 Km. This project has been awarded to the Concessionaire M/s Hyderabad Expressway Private Limited. The Outer Ring Road is to be formed to urban expressway design standards as a dual four-lane carriageway with service roads on either side. The proposed Outer Ring Road also serves as a bypass to important National Highways namely NH-7 and NH-9.
|
| |
Cost and Timeline |
| |
The cost of the project is Rs. 362 crores. The Construction Period is 30 months from the start of the project. The project started from December 20, 2007. |
| |
Highlights |
| |
| Location |
Hyderabad, Andhra Pradesh, |
| Client |
Hyderabad Growth Corridor Ltd. |
| Project |
Construction of eight-lane access controlled expressway on BOT (Annuity) from Bongulur to Tukkuguda |
| Type |
BOT Annuity |
| Cost |
Rs. 362 crores |
| Timeline |
30 months |
| Benefits |
Will contribute to essential infrastructure development in Hyderabad. Will reduce the high traffic congestion in the main city, provides uninterrupted access to new developments like International Airport etc., and will serve as better transportation mode in future. |
| Road length |
Km 108 to Km 121 |
| Length |
13 Kms |
| Concessionaire |
Hyderabad Expressway Pvt. Ltd. |
| Total period |
30 months |
|
| |
|
|
 |